If it takes 100 minutes to complete a circuit, demand at the next work center is 5 parts per minute, and a kanban container holds 20 parts, how many containers are required?

Respuesta :

miamonroe56
miamonroe56 miamonroe56
  • 02-06-2017
5 times 100 = 500
500 divided by 20 = 25
25 containers
Answer Link

Otras preguntas

Need help all mult choice show some type of work/proof
Which of the following reflects the economic theory of mercantilism? A. Merchants should control the government because they contribute more than others to n
Knowing this, you and the company determined that the velocity at which the fireworks should be launched is 224 feet/second. The function that now models the he
need help ASAP with the correct answer!!!!!!
Find the quotient: 15x^4y^2-30x^2y^3+45xy/5xy is ________. when this quotient is divided by _____the result is x^3y-2xy^2+3
Which island group of India lies to its south west ?
The purpose of the air filter is to
Geometry math question
In the 30-60-90 triangle below, side s has a length of _____ and side q has a length of _____.
What happened to the Butterflies in New Jersey as a result if Suburbs being erected & Ddt constantly being sprayed?