32 workers can complete a work in 30 days working 6 hours per day. How many days are required to complete the
same work by 16 workers working 8 hours per day?

Respuesta :

mhanifa
mhanifa mhanifa
  • 03-09-2021

Answer:

  • 45 days

Step-by-step explanation:

Total man hours:

  • 32*30*6 = 5760

Required days:

  • 5760/(16*8) = 45
Answer Link

Otras preguntas

4,720 rounded to the nearest thousand
Drusilla replaces the light bulb in the hall every 9 months and the air filter every 6 mont. she just replaced bot this month. After how many months will she re
Question 1. The opposite of -4 is? A: 4  (picked this one)  B: _4 C: -(-(-4)) D: -|4| Question 2. The opposite of -10 is? A. -(-(-10)) B. -10 C. 10 (picked thi
What is the term used to describe a person who served a ruler or prince? a. courtier b. Renaissance man c. humanist d. sprezzatura
A yard fabric costs $12.99. How much will 2 feet cost?
How do the symptoms of depression compare to those of attempted suicide?
what is the estimate of 92 times 68
do you think northerners were right to stop supporting reconstruction
What is the gcf of 24 30 42
a heartbeat takes 0.8 seconds how many seconds is this written as a fraction