A piece of work takes 20 labourers to complete in 10 days. how many labourers will complete the same job in 25 days if they work at the same rate?​

Respuesta :

denimjackets23
denimjackets23 denimjackets23
  • 04-09-2021

Step-by-step explanation:

If 20 labourers=10 days

x labourers = 25 days

10x= 25×20

[tex] \frac{10x}{10} = \frac{25 \times 20}{10}[/tex]

Cancelling out by 10 on both sides

[tex]x = \frac{25 \times 2}{1} \\ x = 50 [/tex]

Therefore, it takes 50 labourers to complete the work at the same rate in 25 days.

Answer Link

Otras preguntas

Perdita goes to the fruit market with $9 to buy avocadoes. Each avocado costs $2. Write and solve an inequality to find the greatest number of avocadoes Perdita
During World War II, the Battle of Stalingrad took place in __________. a. France c. the Pacific b. Germany d. the Soviet Union
What is 386.05679 rounded to the nearest hundredths ?
Which shows the phrase the product of a number and 3 as a variable expression? A. n+3 B. n-3 C. 3n+3 D. 0.01d + 5( 0.10d)
The acronym rice stands for
What is the discount of 97.99 83.30
Which of the following is a singular noun and verb? a. cheese is b. cheese are c. cheeses are d. cheeses is
The most widely accepted theory among scientists is that the last place humans migrated to was?
Which best describes embryonic stem cells? A.) They are capable of self-renewal only. B.) They are capable of differentiation only. C.) They are capable of self
Which was a major cause of environmental pollution in American cities during the late 1800s? A.dust storms blowing in from the great plains B.wastewater dischar