A plumber laying 500meters of drain pipe requires 20men working for 10days. What length in meters would be laid by 50men in 5days, if they all work at same rate?

Respuesta :

onyebuchinnaji
onyebuchinnaji onyebuchinnaji
  • 06-06-2020

Answer:

50men working in 5days will lay 100 meters

Step-by-step explanation:

If 20men working for 10days lays 500meters

then, 1 man will lay 10,000 meters in 10 days

also, 1 man will lay 1000 meters in 1 day

If 1 man lays 1000 meters in 1 day,

Then, 50 men will lay (1000 meters / 50 );  20 meters in 1 day

also, the same 50 men will lay (20 meters x 5days); 100 meters in 5 days.

Therefore, 50men working in 5days will lay 100 meters

Answer Link

Otras preguntas

Which of the following is true about repetition in an experiment? It involves setting up of a hypothesis. It involves multiple trials. It involves data analy
Why can you multiply unlike terms but not add them?
What is the main idea of the Declaration of Independence
Unsafe and unsanitary work conditions in the early 1900s were a problem leading to the development of
Describe how to transform the graph of f into the graph of g. (1 point) f(x) = x4 and g(x) = -x4
select the expression that is equivalent to (x^4/x^5)^3 a. x/x^2 b. x^7/x^8 c. x^12/x^15 d. x^12/x^5
help easssssssssssssssssy
¿(trabajar) _______ tú por tarde?
Find the derivative of the algebraic function
08.02 CCC Chart and reflection